These items are actively working toward the Freeze Milestone:

Ratification Package

OwnerRatification Plan Ready Date (Target)Specification Freeze Date (Target)Chairs Review (TSC and BoD notified)Arch ReviewWaivers StatusHC/IC Signoff StatusSupporting DocsFreeze ETAPublic Review
ACPISunil VL12/14/2021Q1 2022



Q2'22
AIA (Non-ISA Parts)John Hauser1/2022Q1 20222/23/2022In process

Q3'22
Application Processor-Trusted Execution Environment (AP-TEE)Suresh Sugumar, Ravi Sahita







Architectural Test RequirementsAllen Baum







Debug (Non-ISA Parts)Tim Newsome







IOMMU

4Q2022 ?






IOPMPPaul Ku





Q2'22
Nexus Trace (control)Robert Chyla







PlatformsKumar Sankaran, Atish Patra12/17/20214/18/2022



Q1'23
PLICAbner Chang12/14/202112/21/2021

3/16/2022

4/11/2022None

Q2'22
ProfilesISA chairs12/14/2021Q1 2022



Q2'22
psABIKito Cheng, Jessica Clarke3/20217/20224/13/2022


Q2'22
Unified Discovery (Config)Tim Newsome





Q3'22
WatchdogGreg Favor, Anup Patel1/20212/2022





Zero Trust Platform Security Model

Suresh Sugumar, Ravi Sahita











Notes:

  1. The Non-ISA Document Ratification Template document and the Non-ISA DoD Checklist Template spreadsheet should be copied as a starting point for all non-ISA documents.  Instructions on how to use it are contained within each document.  Please add tech-admin@riscv.org as Editor.
  2. Individual specification ratification document and spreadsheet need to be placed in the RISC-V folder for riscv members → Status → 1 - Ratification Plans → Non-ISA.  Send an email with links to help@riscv.org to request this move.
  3. For more information on the Non-ISA document ratification process, see the Non-ISA Specification Lifecycle (link TBD), Ratification Policy and the Non-ISA Definition of Done Policy documents. To ask any questions about the document and/or to schedule your Chairs Review for the Plan milestone, contact help@riscv.org.

The following items have reached the Frozen milestone and moved onto to the Ratification milestone found on the Non-ISA Vote-Ready Status Dashboard page:

Ratification Package

OwnerRatification Plan Ready DateSpecification Freeze DateChairs Review (TSC and BoD notified)Arch ReviewWaivers StatusHC/IC Signoff StatusSupporting DocsFreeze ETAPublic Review
SBIAtish Patra10/21/202110/27/2021

10/21/2021

CompleteNoneComplete

Q1'2201/10/2022
Processor Trace (e-trace)Gadge Panesar9/22/202111/29/2021

9/22/2021

CompleteNoneComplete

Q1'2201/25/2022
RISC-V UEFI PROTOCOL SpecSunil VL01/26/2022

02/02/2022

01/26/2022In ProcessNoneComplete

Q1'223/23/2022